Explore ClarityA high-priority Metropolitan Water Reclamation District of Greater Chicago (MWRD) Inflow and Infiltration Control Program basin underwent an extensive rehabilitation program.
The project encompassed the design services for the rehabilitation of 8,200 LF of significantly deteriorated 24- to 30-inch pipe within IDOT rights-of-way in a heavily commercialized area. The construction phase included a full-time project representative to oversee the lining of 8,200 LF of 8-, 12-, 24-, and 30-inch-diameter sewers. Other services included permitting (IDOT, MWRD); pre- and post-installation CCTV; construction phasing plans; and bypass pumping planning.
Mike Young, PE
Project Director
Village of Wheeling
Wheeling, Illinois
2018 - 2019
American Public Works Association Suburban Branch 2020 Project of The Year: <$5 million environment category